Stormwater Improvements: The City of Cayce would like to thank you for your patience and continued support of this very important stormwater drainage project.
Phase I, on Blake Drive has been completed.
Phase II, on Delisseline will be completed by January 13th.
Phase III, on Axtell Dr. will begin January 16 and will take less than 5 months.